Anthropic Adds 14.2 Trillion Won in Data Center Capacity as Hyperscaler Lease Bill Hits 1,558 Trillion Won

$10 Billion Lease Deal With Volta Infrastructure Massive Data Center and Power Plant Planned in Texas Five Hyperscalers' Pending Lease Payments Total $1.1 Trillion

International|
|
By Park Yoon-sun
||
null - Seoul Economic Daily International News from South Korea

Anthropic, the operator of Claude, has signed a long-term data center lease agreement worth more than 14 trillion won to secure computing capacity. As projects to build large data centers and power plants for the artificial intelligence (AI) industry heat up worldwide, a survey has also found that the facility and land lease costs the five largest U.S. hyperscalers, or operators of ultra-large data centers, must pay reach 1,558 trillion won.

On the 4th, Bloomberg reported, citing sources, that Anthropic had signed a long-term contract worth $10 billion (about 14.2 trillion won) with Volta Infrastructure, a startup providing graphics processing unit (GPU)-based cloud services.

Volta Infrastructure CEO Ricard Boada said the same day, without naming the counterparty, "We have secured a $10 billion contract over six years with an AI lab." The data center will be built in Norway at a scale of 133 megawatts (MW) and will be equipped with Nvidia's latest "Vera Rubin." Volta recently raised $300 million (about 427.7 billion won) through a funding round, with participation from Nvidia and Dell Technologies Chairman Michael Dell, Bloomberg reported.

Anthropic also plans to use Nexus's ultra-large AI data center campus and its own 1.6-gigawatt (GW) natural gas power plant, which are being built in Texas. Google drew attention by offering to guarantee the project's funding, which reaches $15 billion (about 21 trillion won). In return for the financial support, Google will secure about a 20% stake in the data center and power projects, and Anthropic plans to install AI chips known as tensor processing units (TPUs), which Google co-designed with Broadcom, at the facility. Anthropic has signed more than 10 preliminary data center lease agreements with U.S. developers, and aims to secure at least 10 GW of data center capacity over the coming years.

Amid Surging AI Facility Investment, Pending Payments Alone Reach 1,558 Trillion Won

Inside a Microsoft (MS) data center campus currently under construction. Reuters/Yonhap News

A data center located in Oakland, California, U.S. Reuters/Yonhap News - Seoul Economic Daily International News from South Korea
Inside a Microsoft (MS) data center campus currently under construction. Reuters/Yonhap News A data center located in Oakland, California, U.S. Reuters/Yonhap News

As the AI industry enters a facility investment race, investment has grown astronomically. On the same day, Reuters reported that the amount the five largest U.S. hyperscalers must pay under facility and land lease agreements that have not yet commenced reaches $1.09 trillion (about 1,558 trillion won).

That is nearly four times the $285 billion (about 407 trillion won) in lease liabilities recognized on the balance sheets of the five companies—Amazon, Microsoft, Alphabet, Meta Platforms and Oracle. The $1.09 trillion is mostly related to AI data centers and has not yet been accounted for as liabilities on balance sheets. Signed lease agreements are generally not recognized as liabilities until the facilities become available for use. Until then, only future payments are disclosed in the notes to the financial statements.

Oracle was found to carry the greatest concentration risk. The uncommenced commitments Oracle disclosed amount to $260 billion (about 372 trillion won). That is nearly seven times its recognized lease liabilities of $37.9 billion (about 54 trillion won). Most of the commitments are related to data centers and are scheduled to commence in fiscal years 2027 to 2029, typically lasting 15 to 19 years.

Reuters noted that while these commitments are not hidden, they show that a significant portion of AI build-out projects has not yet been reflected in officially recognized lease liabilities, fixed costs and officially recognized debt metrics.

Meanwhile, Bloomberg reported the same day, citing Citadel Securities, that more than $500 billion (about 715 trillion won) in additional debt will be issued by 2028 to finance the purchase of AI chips for data centers. That is in addition to the $570 billion in existing AI-related debt the market has already absorbed.

Original reporting by Park Yoon-sun for Seoul Economic Daily.

AI-translated from Korean. Quotes from foreign sources are based on Korean-language reports and may not reflect exact original wording.

Watch · Seoul Economic Daily

More →
2:32

AI KEY

Preview
Korean Corporate Intelligence HubKOSPI · KOSDAQ · 12 sectors

A live, cap-weighted view of every KOSPI and KOSDAQ sector, with same-day Korean reporting distilled by company — built for foreign investors, correspondents and analysts who need to scan Korea before the next session.

Korea Company Atlas

Preview
Market Ontology · The Feedback LoopKFTC 2025 · 92 groups · 121,954 articles

An English ontology of the Korean market — how companies, the media, the government and the National Assembly move each other in a loop. Korea's named controlling persons and designated business groups are a mechanism, not a risk to be priced blind.

SIGNAL

Pre-register
English Edition · Capital MarketsM&A · IPO · PE · Fund Flows

Pre-register for SIGNAL English Edition — a premium subscription bringing Korean capital markets coverage (M&A, IPOs, private equity, fund flows) to global institutional investors. First access to the 50% introductory rate.